2002 年 67 巻 555 号 p. 287-293
The previous report (Part 1), reported on the survey and analysis of the labor productivity of the reinforced precast concrete frame (RPC) method, with a focus on on-site work. This report is a continuation of the previous report, with a description of a survey and analysis of labor productivity in the member manufacturing process. The following is a summary of this study. 1. Member manufacturing yield in the precast concrete (PCa) member manufacturing process (1)Work yield by member type (2)Work amount by member section shape (3)Relationship between manufacturing conditions and manufacturing yield (4)Manufacturing yield at the temporary on-site plant 2. Labor productivity of all production activities, from PCa member manufacturing to assembly and joining