単位工期概算式の定式化 : 建設工期の算定方法に関する研究(その3)
加藤 辰彦半田 雅俊石丸 麟太郎笹川 明末永 保美
著者情報
ジャーナル フリー

2004 年 69 巻 584 号 p. 115-120

詳細
抄録

We have been studying the method for calculating the construction period of buildings. In part 3 of this study, we demonstrated the equation to calculate the approximate construction period, in the light of the scale effect of buildings and the self-similarity of construction works. 1) In our conclusion, this-equation of day/m^2 is formularized as form (1). 2) If you wish to calculate the construction period of day more accurately, you should use form (2) and table (3). However, table (3) includes the differences because of the regression coefficients derived from data of buildings constructed. In next part, we will provide more accurate coefficients in form (2) from data of model buildings.

著者関連情報
© 2004 日本建築学会