日本建築学会技術報告集
Online ISSN : 1881-8188
Print ISSN : 1341-9463
ISSN-L : 1341-9463
材料施工
鋼管柱と杭を直接接合する工法の杭工事の施工精度に関する一調査
武田 彰文山本 春行
著者情報
ジャーナル フリー

2011 年 17 巻 36 号 p. 443-448

詳細
抄録

This paper presents the results of pile construction work for two steel-frame buildings. These buildings incorporate a method proposed by the authors in which the bottom end of a steel column is directly connected to the top end of a precast concrete pile. This method, which was developed for the construction of low-rise, long-span, steel-frame buildings, obviates the need for pile caps and underground beams. This method, however, requires greater accuracy in pile construction than is required with conventional construction methods. Hence, a stringent construction control value was specified for the work, and the outcome satisfied this value.

著者関連情報
© 2011 日本建築学会
前の記事 次の記事
feedback
Top