Execution of High-Rise Steel Reinforced Concrete Building
Goten-yama Hills
K. OnoM. YamanouchiH. WamiS. SuzukiT. Tamura
Author information
JOURNAL FREE ACCESS

1990 Volume 28 Issue 2 Pages 50-62

Details
Abstract
The 25-story high-rise complex, in The Goten-yama Hills development project, was designed in “HiRC-II” method. In this building, the shape and dimension of load-gathering structure was unified, so that it became avairable that using some pre-fabricated and systemized members. And also the method of pumping up the column concrete from bottom, placing concrete was not obstacled by the steel beam and reinforced bars, was applied aim to assure the quality and save the durlation of the construction. As the result, it achieved that the durlation needed to construct 1 story was no more than 6 days, and the high-quality S.R.C structure using high-strength concrete was obtained.
Content from these authors
© Japan Concrete Institute
Previous article Next article
feedback
Top