2012 Volume 64 Issue 6 Pages 907-910
Local governments prepared temporary housings for the people who lost their house due to the Great East Japan Earthquake. However the supply of the temporary housing were delayed.
The purpose of this research is to develop effective and efficient supply system of temporary housings by improving the business of local governments.
As a case study, the business process of Ishinomaki city was analyzed in this paper.
As a result, the preparing of the building site was the main factor which cause the delay of supply.
And also, we developed the management model for working processes and resources based on the project management technique.
This idea was applied to verify the proposed model for Ishinomaki city. [This abstract is not included in the PDF]