INFLUENCE OF LENGTH OF TIP HORSE AND POSTURE ON OVERLOAD OF BOOM DEVICE IN BOOM OPERATION OF PLACING CONCRETE BY PUMPING METHOD
Yoshihisa NAKATAShuzo OTSUKAKeiichi OKAMOTOAtsunori MIYATA
Author information
JOURNAL FREE ACCESS

2016 Volume 22 Issue 52 Pages 847-850

Details
Abstract
This paper deals with consideration in boom operation changed length of tip horse to boom and posture of boom in placing concrete by pumping method. Therefore, Quality variation of concrete after pumping show a tendency to almost equal in length pipe for boom. Pressure line for boom should be consideration that length extended pipe line is longer. In addition, Posture of boom should be consideration that take measures to prevent overload for boom as much as type M keep.