A Short Term Construction of Large Buildings by Site-Precast Concrete
The Case of Nikke Community Center
H. SaigaH. TakanoS. NakamuraK. HorikawaI. Haba
Author information
JOURNAL FREE ACCESS

1988 Volume 26 Issue 12 Pages 13-21

Details
Abstract
The construction of Nikke Comunity Center, a large building for shopping with a total floor area of more than 85 000 m2, was required to be completed within only 11.5 months. It was estimated that the conventional cast-in-site concrete construction would need 19 months. The construction, however, was completed as required, adopting the “REQUEST constructing system” which consisted of a framed structure of site-precast concrete such as columns, beams, and stairs, and prefabricated deck-plate forms. This report describes the construction in details.