Development of New Hot-welded Steel Pipe-making Process
Eiji MikamiYoshihiko ShirakawaKuniharu FujimotoJunkichi HamaguchiIchirou Yasumura
Author information
JOURNAL OPEN ACCESS

1991 Volume 31 Issue 6 Pages 635-639

Details
Abstract
A new pipe making process was put into operation at the Kashima Steel Works in 1985. The features of this new pipe-making process are 1) high-temperature welding by use of a high-frequency induction welder, 2) removal of weld bead automatically by use of a specially designed bead-cutting tool just after welding and 3) continuous reheating in the reheating furnace in preparation for the next process, namely stretch reducing.
Content from these authors
© The Iron and Steel Institute of Japan

This is an open access article under the terms of the Creative Commons Attribution-NonCommercial-NoDerivs license.
https://creativecommons.org/licenses/by-nc-nd/4.0/