Abstract
The emergency gas turbine generators offered by IHI Power Systems are designed to supply large volumes of electric power instantaneously in the event of power outages. They are installed in data centers, public facilities, waterworks systems, and other facilities, where they play key roles in ensuring the safety and security of people and society. To meet the growing need for highcapacity generators, we have undertaken component development for higher output compressors and turbine blades to boost the output of 2 MW class gas turbine engines by 25%. This paper describes the efforts to develop compressors and turbines required for highpowered emergency gas turbine.