1974 Volume 1974 Issue 135 Pages 393-399
Succeeding to the previous 1 st report, in which the erection stage was stated to be planned to optimum, the author has introduced another part of SASP (Sasebo Scheduling Programme) which deals with the assembly stage. As the assembling subsystem of the consistent total shipbuilding system naturally takes its own behavior, he has also analyzed its general features, and has concluded that it is especially the essential condition in assembly stage for grasping the process and promoting the efficiency to have workers engage in both fitting and welding works.