Abstract
In this paper, we discuss the resource allocation for the construction scheduling, i. e. we decide the number of the resources and the scheduling each activities with the cost to minimize by the heuristic approach. The heuristic approach repeat to calculate till objective completion date, which is scheduling problem by PERT and date reduction problem by CPM.
In this case, we consider the cost which is to carry in onsite and to carry out from onsite of all the resources. We applied the heuristic approach to the caisson type breakwater construction scheduling, and obtained satisfactory results.