Doboku Gakkai Ronbunshu
Online ISSN : 1882-7187
Print ISSN : 0289-7806
ISSN-L : 0289-7806
DESIGN AND CONSTRUCTION OF FOUNDATION IMPROVEMENT OF COAL STORAGE YARD AT MATSUURA THERMAL POWER PLANT
Yoshiyuki HIRAKAWAYoshio SHINOHARAHiroo MIYAIRI
Author information
JOURNAL FREE ACCESS

1990 Volume 1990 Issue 415 Pages 171-180

Details
Abstract
The Matsuura thermal power plant is a joint undertaking between Kyushu Electric Power Company and Electric Power Development Company. The formar will install two 700MW units and the latter will install two 1000MW coal fired units, having a combined installed capacity of 3400MW which will be the largest coal fired plant in Japan.
This report shows the outline of design and construction of foundation improvement works for the coal storage yard. The sand compaction pile method was adopted to reduce the settlement of coal yard foundation. And the cement stabilization was carried out to improve the surface soil for the stability of stockpile.
Content from these authors
© by Japan Society of Civil Engineers
Previous article Next article
feedback
Top