Abstract
The time for one complete cycle of diaphragm wall excavation by hydraulic bucket was monitored using a special video camera and determined statistically.
A theoretical analysis of the excavation by hydraulic bucket as a variable exacavation problems was also done.
Combining the monitored results and theoretical analysis an estimatin method of the efficiency of diaphragm wall excavation has been proposed.