Abstract
This paper highlights the issues of procurement management in construction projects, such as late delivery of purchased equipments/materials and missing instructions from customers, which cause delays of construction schedule and over-budget cost. We point that most of these problems are caused by lack of synchronization between procurement activities and process control. Therefore, we propose a managerial method which enables better synchronization between the two by applying this method to a construction company. We discuss the necessary conditions and validity of incorporating it and show the way how to establish the mechanics through the case study. Furthermore, we analyze that the feature of this method is not only addressing procurement issues but also bringing additional benefits, such as shortening project lead time and reducing project cost.