Abstract
Generally, many models for large-scale hydraulic test are made from steel and concrete, because it is necessary for them to have strength and durability. Therefore, construction managements that contain safety, accuracy, workability and process control similar to site construction are needed. Although engineers should have knowledge for both general laboratory experiment and site works of construction, there have been no manuals for construction of large-scale model. This is a case study for the large-scale model construction process based on construction of 1/6. 67 scale model used for wave test of the wave power generation facility.