Abstract
This project is Renewal work of TYOMI power station that is the dam type power station that was constructed in 1929. In this project, demolished concrete of about 22,600 m3 was produced by the demolition of the existing structures. Therefore, the recycled aggregate was manufactured by using the aggregate manufacturing equipment which mainly composed of the primary crushing equipment, jaw crusher. Moreover, the recycled coarse aggregate was applied to the existing structures for filling as recycled concrete of about 22,000 m3.