Host: The Japan Society of Mechanical Engineers
Name : Proceedings of FDR2022 International Topical Workshop on Fukushima Decommissioning Research
Date : October 14, 2022 - October 17, 2022
Fauske and Associates (FAI) is performing experiments and modeling for Tokyo Electric Power (TEPCO) for Fukushima fuel debris removal, potential processes, and interim storage. The purpose of our work is to provide a technical basis for TEPCO to select process steps and interim storage options. This paper discusses lessons learned from four recent pertinent projects for damaged fuel remediation: Three Mile Island (TMI), Hanford Spent Nuclear Fuel Project (SNFP), and Sellafield First Generation Magnox Storage Pond (FGMSP), and Sellafield Magnox Swarf Storage Silo (MSSS).