STEEL CONSTRUCTION ENGINEERING
Online ISSN : 1884-0329
Print ISSN : 1880-9928
ISSN-L : 1880-9928
Welding i n Construction of TOKYO WAN AQUA-LINE
-Welding under Low Temperature in Underground Connection of Shield Tunnel-
Yasumasa NAKANISHIJun ISHIITsunayoshi FUNASAKIDaizo TANAKA
Author information
JOURNAL FREE ACCESS

2000 Volume 7 Issue 25 Pages 1-8

Details
Abstract
For TOKYO WAN AQUA-LINE (Traps -Tokyo Bay Highway) the slurry shield method was employed. Because of the long length of tunnel the shield machines from both side were joined under the ground. In this process, the ground freezing method was used as an assistant method and slurry around shield machine was frozen at -30°C. Though machines were also cooled, it was difficult to employ pre- and/or post-heat for prevention from cold cracking. In this study, the welding procedure for water proof and reinforcement welding without pre- and/or post-heat to obtain enough joint strength was examined by experiments. The propriety of welding design was also confirmed in mock-up test. The actual underground connection was finished and TOKYO WAN AQUA-LINE is now under service.
Content from these authors
© Japanese Society of Steel Construction
Next article
feedback