Abstract
Our Kanto Mill Katsuta division is located in the north in Ibaraki prefecture.
Number1power plant of the fuel oil use which is being operated since factory establishment up to now was doing energy supply by only one system. Introduction of new equipment was also urgent business as a production cost measure in addition to shake from production activities of CO2 reduction and fossil fuel dependence.
Necessity in the energy plant where more correspondence to working old replacement of facility and the use energy with the factory production amount rise increase is tight and new than the factory establishment time has occurred.
The form of “thermal recycling” for which a demolition wood is utilized as fuel as well as the “material recycling” which uses a recycled paper for a cardboard raw material from the past are complete by this biomass power plant, and the value as the resource circulation type factory is going to rise more.
It’s introduced about experience from introduction to commercial operation.