KAGAKU KOGAKU RONBUNSHU
Online ISSN : 1349-9203
Print ISSN : 0386-216X
ISSN-L : 0386-216X
An Analysis of a Closed-Circuit Tube-Mill Process to Grind Cement Clinker at Constant Specific Surface Area
Eiichi Onuma
Author information
JOURNAL FREE ACCESS

1975 Volume 1 Issue 4 Pages 351-356

Details
Abstract

Based on operating data of a closed-circuit tube-mill process for cement clinker grinding, the following analysis has been made. First, by applying matrix simulation method, the influence of operating or design variables on the steady-state flowrate (P) and particle-size distribution of fine products has been estimated, under the condition that the specific surface of fine products (Sp) is always kept constant by adjusting cut-size of classifier. Next, based on the estimation, some fundamental ideas to optimize operating and design variables have been found out. Main conclusions are as follows.
1) The flowrate of classifier feed (F) to maximize P is strongly dependent on the flowrate of circulating air in the classifier, but is independent of aimed value of Sp. On the other hand, circulating load to maximize P is strongly dependent on aimed Sp. 2) To reduce the specific energy consumption, it is important to select the appropriate capacity ratio of classifier to mill, and also to maintain F at the optimum point.

Content from these authors
© by THE SOCIETY OF CHEMICAL ENGINEERS, JAPAN
Previous article Next article
feedback
Top