Abstract
It is possible that workers' error, variation of processing time, lack of parts and machine failure
will affect the delivery date of each production process. The consecutive delay in the process can lead to the
postponing of manufacturing production. By optimizing the workers' assignments, it is possible to achieve the
delivery date of the product and reduce the total expected cost of the product. This study takes a parallel production
line as an example and considers the problem of optimal assignment of workers to each process when the
target processing time follows a continuous distribution to minimize the total expected cost.