2002 Volume 9 Pages 11-17
CM (Construction Management) system is recently considered to apply to dam projects in order to clear the profile of construction costs. In this paper, we have compared usual one-package order with separated order by CM system in the case of fill-dam project that requires the strong unity of quarry activities with filling activities. In the consequence, it is cleared the problems newly arisen to construction site management, responsibility and risk for construction manager, and the tendency of increase of total risks in the case of introducing separated order by CM system into fill-dam projects.