1991 Volume 4 Issue 1 Pages 38-44
The preliminary design of the Japanese Experiment Module (JEM) started in January 1990, and the first and second interim design reviews were held in July 1990 and February 1991 respectively. As a result of the JEM configuration review activity and the technical interface coordination with NASA through the Environmental Control and Life Support System (ECLSS) working group meetings, a part of the JEM ECLSS function was changed. This paper presents the JEM ECLSS baseline and the subsystem configuration at the second interim design review. Also the outline of the preliminary cabin air ventilation testing which was conducted from 1989 to 1990 is described.