Abstract
It is not easy for IT projects to apply EVM methodology because project data collection is not sufficiently controlled. On the other hand, Cost-of-Quality has been managed from recognition of the importance of quality. This article presents new quality-value focused EVM method, which support project visualization and control from the integrated viewpoint of quality, cost, and schedule. It is possible to interpret Quality-Value in conformity with management data which could be different depending on project management maturity levels. Finally, some cases applied to actual projects are introduced and the effectiveness of this method is explained.