2020 Volume 26 Issue 63 Pages 667-671
Affected by the Great East Japan Earthquake and the Fukushima Daiichi Nuclear Power Station Accident, about 16,800 temporary housing was built in Fukushima Prefecture. Among these, 13,408 of built temporary housing, which was built by purchase method of Fukushima Prefecture, was the subject to reuse after their supply period. This research revealed the actual conditions of the temporary housing by the examination and the analysis of framework of reuse system established by Fukushima Prefecture and a case study of relocation and reuse, which were conducted by “transfer”, as a main target.
Ethical standards of the publisher (‘Ethical Standards Concerning the Peer Review for the Presentation of Architectural Transactions and Works’)