2022 Volume 28 Issue 70 Pages 1500-1505
We clarified the role of CMR and other stakeholders in the complex public facility development of small municipality by analyzing the minutes and documents used in the development. In (Part 1) CMR and the expert committee as two wheels could implement to prevent from the unsuccessful bid and to adopt the ECI method through the procurement process. Furthermore, small municipality that do not have sufficient internal and technical experts could carry out large-scale construction project supported by not only CMR but also the expert committee.