SURVEY ON CURING MANAGEMENT DURING HEAT CURING IN COLD WEATHER CONCRETING
Kazuhiro FURUKAWATakayuki FUKASETakahiro CHIBA
Author information
JOURNAL FREE ACCESS

2025 Volume 31 Issue 77 Pages 52-56

Details
Abstract

In this study, we surveyed the actual conditions of adjustment and management of curing temperature and heating equipment in heat curing for 33 cold weather concrete works. As a result, the difference between the planned and actual values of curing temperature was 5°C or more and less than 10°C in 39% of the works, and heating adjustment was assumed to have been performed in 64% of the works. In addition, the curing temperature management could have been optimized by reviewing the predicted average temperature immediately before construction in 64% of the works.