Abstract
It was examined that the possibility of the introduction of the solar photovoltaic generation and wind power generation in a lot of abandoned farmland in Wakayama pref. We did a screening with electric grid and wind speed data, and visualized some applicable areas in Wakayama pref. by Geographic Information System based on statistics. In addition, we interviewed every municipality to ask them how the abandoned farmlands were managed. We found that 45 abandoned farmlands which are greater than 2ha existed in Wakayama pref. In addition, we revealed 22 proper areas for solar photovoltaic generation and 5 proper areas for wind power generation.