Abstract
The first stage construction of the city hall of Sakata was completed in December 2015, and the second stage construction was completed in June 2017. It is currently in operation and heat source system and air conditioning system have been operating smoothly. In addition, the heat source system satisfies the expected performance. This paper describes the outline of the thermal response, the results of heating operation in the winter season and cooling operation in the summer season.