2009 Volume 129 Issue 10 Pages 1174-1180
Analysis of the EMTP transformer model was performed with the 4kVA two windings low voltage transformer with the current injection (CIJ) measurement method to study a transient recovery voltage (TRV) at the transformer limited fault (TLF) current interrupting condition. Tested transformer's impedance was measured by the frequency response analyzer (FRA). From FRA measurement graphs leakage inductance, stray capacitance and resistance were calculated. The EMTP transformer model was constructed with those values. The EMTP simulation was done for a current injection circuit by using transformer model. The experiment and simulation results show a reasonable agreement.