玄海原子力発電所の運転実績
井地 輝雄西川 正行
著者情報
ジャーナル フリー

1977 年 19 巻 5 号 p. 299-302

詳細
抄録

Genkai Nuclear Power Station Unit 1 owned by the Kyushu Electric Power Co., the 8th LWR in Japan, commenced the commercial operation on Oct. 15, 1975, and achieved the longest (243 days) continued operating record of the LWR in Japan in the first cycle.
After 14, 350 MWD/t of average burn up was attained, the first annual inspection and refueling was performed satisfactorily as the plan during the 86 days outage period-from Oct. 31, 1976 to Jan. 24, 1977. Now the unit is generating full power of 559 MW. Summary of the operating experience of the unit from the commencement of operation is briefly described in this report.