Abstract
Long term field measurement has been conducted on the shield tunnel deformation over 20 years, which has been planned to be employed for the Tokyo Bay area rapid transit train system. The measurement results have been quite different from the predicted. Three dimensional finite element analysis has been performed, which takes account of actual geological conditions and the variation of drainage condition along the shield tunnel lining due to the severe longitudinal deformation of the tunne