1986 年 1986 巻 366 号 p. 163-166
In order to produce the prepacked concrete of high quality, it is important to fill up the voids of preplaced coarse aggregate with mortar perfectly.
The author had proposed a theoretical method for predicting the process that the voids of the coarse aggregate were grouted.