Abstract
Damage of coming Nankai Trough Earthquake is thought to be larger than Tohoku Earthquake in 2011, there is concern that reconstruction will takes long period. Housing relocation projects of Higashi-Matsusima city after Tohoku Earthquake were analyzed, prototype of Housing relocation projects which is categorized 4 pattern were established in this study. Based on these prototype and damage estimate of Konan city by coming Nankai Trough Earthquake, housing relocation projects of Konan city was established. Then, 4 scenarios reconstruction schedules which have difference whether the municipal government have “pre-earthquake plan for relocation” and “enough temporary pile yard for disaster waste” or not were compared, effectively of these measures were analyzed quantitatively. This kind of analysis method thought to be effective to find out good reconstruction plan by information sharing of reconstruction procedure between municipal government and residents.