Doboku Gakkai Ronbunshuu D
Online ISSN : 1880-6058
ISSN-L : 1880-6058
Technical Report (In Japanese)
A STUDY OF CONSTRUCTION EXECUTION OF PERMEABLE SLAG ROADBED FOR RAILWAY TUNNEL
Makoto SUNAGAYuji MATSUMOTOHiroshi OHSHIMATakashi YAOYAMA
Author information
Keywords: slag, shirasu, roadbed, tunne
JOURNAL FREE ACCESS

2008 Volume 64 Issue 3 Pages 411-420

Details
Abstract
The permeable roadbed using the slug materials is adopted in the tunnel under the Shirasu ground water level on the Kyushu Shincansen started in March, 2004. The purpose of permeable roadbed is decline of ground water level and prevention against the mud-pumping of Shirasu by trainload. The study which is related to the structure of permeable roadbed has already been reported.
This paper describes a result of variety execution confirmation examination about the way of slag compaction, the method of the quality control, and so on.
Content from these authors
© 2008 by Japan Society of Civil Engineers
Previous article Next article
feedback
Top