Abstract
To reinforce an existing revetment and utilize effectively the soft dredged soil, we created the reclaimed shallow place using the improved dredged soil by converter slag. As for prior examination, we designed required strength of the improved soil and determined the blending condition. Then, we verified the reinforcing effect and decreasing overtopping wave by analysis.
In this paper, we describe the method of prior examination, and clarified the result of the quality control and survey of water quality.