Abstract
The solution for source transfer time beyond criteria problem in LingAo project II is introduced in the paper. System is modified and criteria are updated. Analysis and tests are performed to get proper parameter. International rules are used to evaluate the new criteria. The problem is solved finally, contributing stable power supply to unit pre-operation, start-up and operation. Experience also gathered for CPR1000 new projects.