羽田空港D滑走路建設工事における長期的な圧密沈下予測について
水野 健太渡部 要一小林 正樹野口 孝俊青木 康哲山本 隆信高橋 充
著者情報
ジャーナル フリー

2012 年 61 巻 1 号 p. 78-84

詳細
抄録

In the construction of the D-runway in Tokyo International Airport (Haneda Airport), “the settlement prediction and management system (HSAP)” which can efficiently evaluate the consolidation settlement of artificial reclamation was developed. The reclamation history data base which reflected the actual construction until July, 2009 and the reclamation plan after that was made. The actual measurement and the calculation value were compared and the various consolidation parameters were identified. Moreover, the long-term consolidation test and constant strain rate consolidation test were executed, and the secondary consolidation parameter was set based on the isotache model's concept. Based on the prediction result of the residual consolidation settlement, the filling height of the D-runway at the start of in-service period was decided to be 0.70m, which is required from the aviation operation.

著者関連情報
© 2012 日本材料学会
前の記事 次の記事
feedback
Top