The new system is, in a word, to make an order list after the completion of cutting plan in 1/10 scale. The system has been applied to a material order of 67,000-dwt. foreign tanker whose keel was laid in August 1964, and attained the following distinguished results. 1. The material can be ordered to fully match its use in shop. 2. Loss of material is minimized and re-layout is not required so far as no change is made in design. In consequence, scrap percentage of material can be extensively decreased. 3. Closer and earlier planning of production and material control can be expected. The system has been fortunately carried in effect and all the material ordered with the positive cooperation of all the departments in our yard; desired results have been attained. From now on, therefore, we intend to apply this system, as much as possible, to all ships to be constructed in our shipyard.