動的計画法を用いた坑内充填採掘の多期間生産計画に関する研究
陳 慶華山冨 二郎茂木 源人安達 毅
著者情報
ジャーナル フリー

2001 年 117 巻 11 号 p. 855-861

詳細
抄録
A multi-period planning model for underground cut-and-fill operations was constructed for the purpose of maximizing discounted profit under given production constraints. The ore grades were estimated through geostatistics for minimizing the estimation errors, and production costs were calculated on the basis of the practical operation data. A sequential planning algorithm based on dynamic programming (DP) was then developed to specify the most profitable mining sequence, and applied to a Chinese copper-iron mine employing cut-and-fill stoping. Calculation results showed that the proposed DP-based sequential planning strategy can produce larger discounted profits than those obtained by the advance and retreat mining sequences.
著者関連情報
© 2001 by The Mining and Materials Processing Institute of Japan