日本鉱業会誌
Online ISSN : 2185-6729
Print ISSN : 0369-4194
石炭荷役における配船計画決定の一手法
籏崎 裕章
著者情報
ジャーナル フリー

1983 年 99 巻 1143 号 p. 365-370

詳細
抄録

It is important to determine the scale of coal receiving bases and to operate it economically because coal firing thermal power plants have come into the limelight again and a lot of coals have been imported directly by ocean shipment.
The main results in this paper are as follows;
1) The scale of coal receiving bases including the number of berth, the coal storage yard capacity and unloader capacity is determined by the theory of probability.
2) A program to operate the determined scale of facilities on economical condition can be maid by the methods mentioned below;
a) The numbers of days spent by a voyage of a coaler are approximated by a normal distribution as they are dependent on the weather and other conditions.
b) The expected value that a volume of coal storage hits the upper (or lower) limits of a yard capacity after (or before) arrival of ships arranged by the pre-determined coal consumption program is calculated by using the theory of probability.
c) The shipping schedule is determined by the Branch and Bound Method under a condition that the annual cumulative expected value is minimized.