2022 年 28 巻 69 号 p. 953-957
This study analyzed the operational status of 18 districts to which the tsunami reconstruction base development project established for the reconstruction after Great East Japan Earthquake was applied. As a result, the following three points were mainly clarified. Of the 7 districts that were gradually expanded, 5 districts including the land readjustment project were 10ha or less, and 5 districts with an applicable area of 5ha or less were slow to introduce the project and only public facilities were developed. 7 districts with more than 10ha were not merged with the land readjustment project except Rikuzentakata City.