2025 年 31 巻 77 号 p. 52-56
In this study, we surveyed the actual conditions of adjustment and management of curing temperature and heating equipment in heat curing for 33 cold weather concrete works. As a result, the difference between the planned and actual values of curing temperature was 5°C or more and less than 10°C in 39% of the works, and heating adjustment was assumed to have been performed in 64% of the works. In addition, the curing temperature management could have been optimized by reviewing the predicted average temperature immediately before construction in 64% of the works.