主催: 社団法人 日本エネルギー学会
会議名: 第34回石炭科学会議
回次: 34
開催地: 仙台
開催日: 1997/10/30 - 1997/10/31
p. 143-146
After completion of the construction, 150t/d Bituminous coal liquefaction pilot plant was in operation phase, July in 1996. It was operated for commissioning, hot oil circulation, shakedown operation during nine month till March 1997. After shakedown operation, it was successfully operated twice without any serious trouble and especially in the second operation (Run-2), it was continuously operated during 1012 hours. In this paper, we present especially the operating profile of Run-2 and test results of coal liquefaction reactors.