Enhanced Resource-Dependent Critical Path Method for Identifying Resource Dependencies in Variable Resource Constrained Project
Salman Ali NISARKoshi YAMAMOTOKoji SUZUKI
著者情報
ジャーナル フリー

2013 年 69 巻 2 号 p. I_110-I_120

詳細
抄録

 This paper proposes the enhanced resource-dependent critical path method (enhanced RDCPM) for identifying resource dependencies that exist between activities in order to compute the correct floats and determine the critical path in the project schedule under variable resource constraints. In addition to technological relations, there exist resource dependencies between activities in a project schedule under resource constraints that are neglected in traditional resources constrained scheduling (RCS) techniques. Therefore RCS cannot compute the correct floats and critical path(s). Although previous studies have proposed many methods in order to overcome these shortcomings, they assumed that the maximum amount of available resources remains constant during the execution of the project. However, an actual project can have variable resource constraints in certain situations. The enhanced RDCPM, which is an improved version of the RDCPM, reasonably identifies the resource dependencies between activities and computes the correct floats and critical path in a project schedule under either variable or constant resource constraints. Moreover, it provides an updateable schedule with stable work sequences. Therefore, the enhanced RDCPM can be adapted for scheduling and control in real construction projects.

著者関連情報
© 2013 Japan Society of Civil Engineers
前の記事 次の記事
feedback
Top