加速器
Online ISSN : 2436-1488
Print ISSN : 1349-3833
話題
RIBF加速器のビームコミッショニング
福西 暢尚
著者情報
ジャーナル フリー

2007 年 4 巻 2 号 p. 112-122

詳細
抄録

RIKEN Nishina Center started commissioning of the RI Beam Factory accelerator complex in July 2006. We succeeded in extracting the first beams from the fixed-frequency Ring Cyclotron, Intermediate-stage Ring Cyclotron and Superconducting Ring Cyclotoron on September 29, November 22 and December 28, 2006, respectively. We also accelerated a uranium beam up to 345 MeV/u using all the cyclotrons newly constructed in the RIBF project in march 2007. Our progress on commissioning of RIBF accelerator complex will be outlined.