Abstract
This study deals with proactive scheduling approach in which dummy jobs are inserted into a schedule in order to absorb impacts of uncertain events such as urgent jobs, machine breakdowns,and so on. This paper extends our previous work to flow shop scheduling problems with limited intermediate storages.We also propose an analytical model which determines a suitable amount of dummy jobs to be inserted into a predictive schedule.Some computational experiments demonstrate that the proposed proactive scheduling is effective by comparing it with predictable scheduling rules.