In connection with the detailed planning and scheduling for construction process, we studied characteristics of construction process, and pointed out required items of planning and scheduling procedure. This paper proposed new systematical methods based on "Construction Process Chart" to make appropriate representation of detailed planning of construction process. In addition, these methods clear the sequence of Works, job-sites, resources, then solve resource levelling and term shortening problems o, n a construction project. The proposed methods have procedures for representing construction works into detailed process, and adapted to the practical works, which proved that methods would greatly contribute to the successful usage of construction planning phase.