The previously reported papers proposed new systematical methods based on "Construction Process Chart" to solve resource levelling and term shortening problems on a construction project, and then the proposed metods were adapted to the some practical structural works, which proved they would greatly contribute to the successful usage of construction planning phase. In connection with the detailed planning and scheduling for construction process, this paper cleared characteristics of interior finishing works, and pointed out essential algorithm of pllanining and scheduling procedure. Moreover, the autor adapted these methods to the practical interior finishing works, which examined effectiveness of them as much great usefulness as the practical structural works.