抄録
This study presents the rational approaches to the process planning and scheduling for a building construction with computer systems. In the paper, the author put the focus on the methodology for planning and scheduling of ,an outline of construction process, using the mathematical models which are based on goal programming, In the models, the precedences among activities were represented by network notations with time lags. The author modified the specified time lags among activities in order to meet the mandatory date for completion and to balance the process according to the precedences relationships to be specified. The method developed here were applied to planning of an office building construction, then the author concluded that the method developed will be a useful tool for planning stage of building construction, and will generate promptly the rational alternatives for construction engineers.